Project Description:
148 metre overall length, composite steel and timber spiraled cycle way. The strength of the structure stems from the fabricated trapezoidal box section running continuously along one side of the main deck, switching at the centre point, with a steel cantilever frame forming the deck support system. Modular construction techniques were employed to build complete sections off site aiding a swift, if complex, installation process. The integrated lighting design was developed and designed by Britons and utilizing its close-knit supply chain. Timber deck boards and “lean” boards add to the overall Architectural status of this stunning structure.
Project Details:
CLIENT:
VolkerFitzpatrick
CONTRACT AWARD:
February 2016
TONNAGE:
170t
COMPLETION DATE:
December 2017